Risk management and mitigation in major defense acquisition programs and major systems
10 U.S.C. § 4212
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Requirement.—
The Secretary of Defense shall ensure that the initial acquisition strategy (required under section 4211 of this title) approved by the milestone decision authority and any subsequent revisions include the following:
A comprehensive approach for managing and mitigating risk (including technical, cost, and schedule risk) during each of the following periods or when determined appropriate by the milestone decision authority:
Approach to Manage and Mitigate Risks.—
The comprehensive approach to manage and mitigate risk included in the acquisition strategy for purposes of subsection (a)(1) shall, at a minimum, include consideration of risk mitigation techniques such as the following:
Preference for Prototyping.—
To the maximum extent practicable and consistent with the economical use of available financial resources, the milestone decision authority for each major defense acquisition program shall ensure that the acquisition strategy for the program provides for—
Concurrency Defined.—
In this section, the term “concurrency” means, with respect to an acquisition strategy, the combination or overlap of program phases or activities.(Added Pub. L. 114–92, div. A, title VIII, § 822(a)(1), Nov. 25, 2015, 129 Stat. 900, § 2431b; amended Pub. L. 114–328, div. A, title X, § 1081(a)(7), Dec. 23, 2016, 130 Stat. 2417; renumbered § 4212 and amended Pub. L. 116–283, div. A, title XVIII, § 1847(b)(3), Jan. 1, 2021, 134 Stat. 4254.)