Plant or construction projects for which amounts are made available under this and subsequent appropriation Acts 1 with a current estimated cost of less than $10,000,000 are considered for purposes of section 6273 as a plant project for which the approved total estimated cost does not exceed the minor construction threshold and for purposes of section 6275 as a construction project with a current estimated cost of less than a minor construction threshold.
(Added Pub. L. 119–60, div. C, title XXXI, § 3111(a), Dec. 18, 2025, 139 Stat. 1427.)