Rulemaking requirement
Not later than 1 year after August 8, 2005, the Commission shall establish, by rule, incentive-based (including performance-based) rate treatments for the transmission of electric energy in interstate commerce by public utilities for the purpose of benefitting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion.
Contents
The rule shall—
allow recovery of—
Incentives
In the rule issued under this section, the Commission shall, to the extent within its jurisdiction, provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization. The Commission shall ensure that any costs recoverable pursuant to this subsection may be recovered by such utility through the transmission rates charged by such utility or through the transmission rates charged by the Transmission Organization that provides transmission service to such utility.
Just and reasonable rates
All rates approved under the rules adopted pursuant to this section, including any revisions to the rules, are subject to the requirements of sections 824d and 824e of this title that all rates, charges, terms, and conditions be just and reasonable and not unduly discriminatory or preferential.