Definitions.—
Eligible project or activity.—
In general.—
In this section, the term “eligible project or activity” means a project or activity within an existing operational right-of-way (as defined in section 771.117(c)(22) of title 23, Code of Federal Regulations (or successor regulations))—
that is—
that—
Exclusion.—
The term “eligible project or activity” does not include a project to create a new travel lane.Preliminary evaluation.—
The term “preliminary evaluation”, with respect to an application described in subsection (b)(1), means an evaluation that is customary or practicable for the relevant agency to complete within a 45-day period for similar applications.Relevant agency.—
The term “relevant agency” means a Federal agency, other than the Federal Highway Administration, with responsibility for review of an application from a State for a permit, approval, or jurisdictional determination for an eligible project or activity.Action Required.—
In general.—
Subject to paragraph (2), not later than 45 days after the date of receipt of an application by a State for a permit, approval, or jurisdictional determination for an eligible project or activity, the head of the relevant agency shall—
Extension.—
The head of the relevant agency may extend the review period under paragraph (1) by not more than 30 days if the head of the relevant agency provides to the State written notice that includes an explanation of the need for the extension.Failure to act.—
If the head of the relevant agency fails to meet a deadline under paragraph (1) or (2), as applicable, the head of the relevant agency shall—