Water resources development project defined
In this section, the term “water resources development project” means a project recommendation that results from—
Authority
In general
A non-Federal interest may carry out a federally authorized water resources development project, or separable element thereof—
Conditions
Before carrying out a water resources development project, or separable element thereof, under this section, a non-Federal interest shall—
Permit exception
In general
For a project described in subsection (a)(1) or subsection (a)(3), or a separable element thereof, with respect to which a written agreement described in subparagraph (B) has been entered into, a non-Federal interest that carries out a project under this section shall not be required to obtain any Federal permits or approvals that would not be required if the Secretary carried out the project or separable element unless significant new circumstances or information relevant to environmental concerns or compliance have arisen since development of the project recommendation.
Written agreement
For purposes of this paragraph, a written agreement shall provide that the non-Federal interest shall comply with the same legal and technical requirements that would apply if the project or separable element were carried out by the Secretary, including all mitigation required to offset environmental impacts of the project or separable element as determined by the Secretary.
Certifications
Notwithstanding subparagraph (A), if a non-Federal interest carrying out a project under this section would, in the absence of a written agreement entered into under this paragraph, be required to obtain a certification from a State under Federal law to carry out the project, such certification shall still be required if a written agreement is entered into with respect to the project under this paragraph.
Data sharing
In general
If a non-Federal interest for a water resources development project begins to carry out that water resources development project under this section, the non-Federal interest may request that the Secretary transfer to the non-Federal interest all relevant data and documentation under the control of the Secretary with respect to that water resources development project.
Deadline
Except as provided in subparagraph (C), the Secretary shall transfer the data and documentation requested by a non-Federal interest under subparagraph (A) not later than the date that is 90 days after the date on which the non-Federal interest so requests such data and documentation.
Limitation
Nothing in this paragraph obligates the Secretary to share any data or documentation that the Secretary considers to be proprietary information.
Studies and engineering
In general
When requested by a non-Federal interest carrying out a project or separable element of a project under this section, the Secretary shall undertake all necessary studies, engineering, and technical assistance on construction for any project or separable element of a project under this section, and provide technical assistance in obtaining all necessary permits for the construction, if the non-Federal interest contracts with the Secretary to provide funds to the United States for the studies, engineering, or technical assistance.
No waiver
Nothing in this section may be construed to waive any requirement of section 3142 of title 40.
Limitation
Funds provided by non-Federal interests under this subsection shall not be eligible for credit or reimbursement under subsection (d).
Impartial decisionmaking
In carrying out this section, the Secretary shall ensure that the use of funds accepted from a non-Federal interest will not affect the impartial decisionmaking of the Secretary, either substantively or procedurally.
Credit or reimbursement
General rule
Subject to paragraph (3), a project or separable element of a project carried out by a non-Federal interest under this section shall be eligible for credit or reimbursement for the Federal share of work carried out on a project or separable element of a project if—
before initiation of construction of the project or separable element—
Application of credit
The Secretary may apply credit toward—
Requirements
The Secretary may only apply credit or provide reimbursement under paragraph (1) if—
the Secretary certifies that the project, discrete segment of the project, or separable element of the project has been constructed in accordance with—
Monitoring
The Secretary shall regularly monitor and audit any water resources development project, or separable element of a water resources development project, constructed by a non-Federal interest under this section to ensure that—
Discrete segments
In general
The Secretary may authorize credit or reimbursement under this subsection for carrying out a discrete segment of a federally authorized water resources development project, or separable element thereof, before final completion of the project or separable element if—
Determination
Credit or reimbursement may not be made available to a non-Federal interest pursuant to this paragraph until the Secretary determines that—
Written agreement
In general
As part of the written agreement required under paragraph (1)(A)(iii), a non-Federal interest to be eligible for credit or reimbursement under this paragraph shall—
Remittance
If a non-Federal interest fails to complete a water resources development project, or separable element thereof, that it agreed to complete under clause (i)(II), the non-Federal interest shall remit any reimbursements received under this paragraph for a discrete segment of such project or separable element.
Discrete segment defined
In this paragraph, the term “discrete segment” means a physical portion of a water resources development project to be carried out, or separable element thereof—
Exclusions
The Secretary may not provide credit or reimbursement for—
Notification of committees
If a non-Federal interest notifies the Secretary that the non-Federal interest intends to carry out a project, or separable element thereof, under this section, the Secretary shall provide written notice to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives concerning the intent of the non-Federal interest.
Operation and maintenance
Assumption of maintenance
Whenever a non-Federal interest carries out improvements to a federally authorized harbor or inland harbor, the Secretary shall be responsible for operation and maintenance in accordance with section 2211(b) of this title if—
before construction of the improvements—
Federal financial participation in the costs of a locally preferred plan.
In the case of improvements determined by the Secretary pursuant to paragraph (1)(A)(i) to deviate from the national economic development plan, the Secretary shall be responsible for all operation and maintenance costs of such improvements, as described in section 2211(b) of this title, including costs in excess of the costs of the national economic development plan, if the Secretary determines that the improvements satisfy the requirements of paragraph (1).
(Pub. L. 99–662, title II, § 204, Nov. 17, 1986, 100 Stat. 4099; Pub. L. 101–640, title III, § 303, Nov. 28, 1990, 104 Stat. 4634; Pub. L. 113–121, title I, § 1014(b)(1), June 10, 2014, 128 Stat. 1220; Pub. L. 114–322, title I, § 1127, Dec. 16, 2016, 130 Stat. 1648; Pub. L. 115–270, title I, § 1153, Oct. 23, 2018, 132 Stat. 3789; Pub. L. 116–260, div. AA, title I, § 105(a), (b), Dec. 27, 2020, 134 Stat. 2622; Pub. L. 118–272, div. A, title I, § 1110(a), Jan. 4, 2025, 138 Stat. 3009.)