U.S. Code · Título 33
Planning
33 U.S.C. § 2282a
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Omitted
Planning process improvements
The Chief of Engineers—
not later than one year after November 8, 2007, shall—
Benchmarks
In general
Not later than 12 months after November 8, 2007, the Chief of Engineers shall establish benchmarks for determining the length of time it should take to conduct a feasibility study for a water resources project and its associated review process under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). The Chief of Engineers shall use such benchmarks as a management tool to make the feasibility study process more efficient in all districts of the Corps of Engineers.
Benchmark goals
The Chief of Engineers shall establish, to the extent practicable, under paragraph (1) benchmark goals for completion of feasibility studies for water resources projects generally within 2 years. In the case of feasibility studies that the Chief of Engineers determines may require additional time based on the project type, size, cost, or complexity, the benchmark goal for completion shall be generally within 4 years.
Calculation of benefits and costs for flood damage reduction projects
A feasibility study for a project for flood damage reduction shall include, as part of the calculation of benefits and costs—
Centers of specialized planning expertise
Establishment
The Secretary may establish centers of expertise to provide specialized planning expertise for water resources projects to be carried out by the Secretary in order to enhance and supplement the capabilities of the districts of the Corps of Engineers.
Duties
A center of expertise established under this subsection shall—
Deep draft navigation planning center of expertise
In general
The Secretary shall consolidate deep draft navigation expertise within the Corps of Engineers into a deep draft navigation planning center of expertise.
List
Not later than 60 days after the date of the consolidation required under subparagraph (A), the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a list of the grade levels and expertise of each of the personnel assigned to the center described in subparagraph (A).
Completion of Corps of Engineers reports
Alternatives
In general
Feasibility and other studies and assessments for a water resources project shall include recommendations for alternatives—
Constraints
The alternatives contained in studies and assessments described in subparagraph (A) shall not be constrained by budgetary or other policy.
Reports of Chief of Engineers
The reports of the Chief of Engineers shall identify any recommendation that is not the best technical solution to water resource needs and problems and the reason for the deviation.
Report completion
The completion of a report of the Chief of Engineers for a water resources project—
shall be submitted, on completion, to—
Completion review
In general
Except as provided in paragraph (2), not later than 120 days after the date of completion of a report of the Chief of Engineers that recommends to Congress a water resources project, the Secretary shall—
Prior reports
Not later than 180 days after November 8, 2007, with respect to any report of the Chief of Engineers recommending a water resources project that is complete prior to November 8, 2007, the Secretary shall complete review of, and provide recommendations to Congress for, the report in accordance with paragraph (1).
(Pub. L. 110–114, title II, § 2033, Nov. 8, 2007, 121 Stat. 1084; Pub. L. 113–121, title II, § 2103, June 10, 2014, 128 Stat. 1278.)