U.S. Code · Título 33
Monitoring ecosystem restoration
33 U.S.C. § 2330a
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
In general
In conducting a feasibility study for a project (or a component of a project) for ecosystem restoration, the Secretary shall ensure that the recommended project includes, as an integral part of the project, a plan for monitoring the success of the ecosystem restoration.
Monitoring plan
The monitoring plan shall—
Cost share
For a period of 10 years from completion of construction of a project (or a component of a project) for ecosystem restoration, the Secretary shall consider the cost of carrying out the monitoring as a project cost. If the monitoring plan under subsection (b) requires monitoring beyond the 10-year period, the cost of monitoring shall be a non-Federal responsibility.
Inclusions
A monitoring plan under subsection (b) shall include a description of—
Conclusion of operation and maintenance responsibility
The responsibility of a non-Federal interest for operation and maintenance of the nonstructural and nonmechanical elements of a project, or a component of a project, for ecosystem restoration shall cease 10 years after the date on which the Secretary makes a determination of success under subsection (b)(2).
Federal obligations
The Secretary is not responsible for the operation or maintenance of any components of a project with respect to which a non-Federal interest is released from obligations under subsection (e).
(Pub. L. 110–114, title II, § 2039, Nov. 8, 2007, 121 Stat. 1100; Pub. L. 114–322, title I, § 1161, Dec. 16, 2016, 130 Stat. 1668.)