Definitions
In this section:
Environmental impact statement
The term “environmental impact statement” means the detailed statement of environmental impacts of a project required to be prepared pursuant to the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
Environmental review process
In general
The term “environmental review process” means the process of preparing an environmental impact statement, environmental assessment, categorical exclusion, or other document under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for a project study.
Inclusions
The term “environmental review process” includes the process for and completion of any environmental permit, approval, review, or study required for a project study under any Federal law other than the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
Federal jurisdictional agency
The term “Federal jurisdictional agency” means a Federal agency with jurisdiction delegated by law, regulation, order, or otherwise over a review, analysis, opinion, statement, permit, license, or other approval or decision required for a project study under applicable Federal laws (including regulations).
Federal lead agency
The term “Federal lead agency” means the Corps of Engineers.
Project
The term “project” means a water resources development project to be carried out by the Secretary.
Project sponsor
The term “project sponsor” has the meaning given the term “non-Federal interest” in section 1962d–5b(b) of title 42.
Project study
The term “project study” means a feasibility study for a project carried out pursuant to section 2282 of this title.
Applicability
In general
This section—
Flexibility
Any authority granted under this section may be exercised, and any requirement established under this section may be satisfied, for the conduct of an environmental review process for a project study, a class of project studies, or a program of project studies.
List of project studies
In general
The Secretary shall annually prepare, and make publicly available, a separate list of each study that the Secretary has determined—
Inclusions
The Secretary shall include for each project study on the list under subparagraph (A) a description of the estimated amounts necessary to make substantial progress on the project study.
Project review process
In general
The Secretary shall develop and implement a coordinated environmental review process for the development of project studies.
Coordinated review
The coordinated environmental review process described in paragraph (1) shall require that any review, analysis, opinion, statement, permit, license, or other approval or decision issued or made by a Federal, State, or local governmental agency or an Indian tribe for a project study described in subsection (b) be conducted, to the maximum extent practicable, concurrently with any other applicable governmental agency or Indian tribe.
Timing
The coordinated environmental review process under this subsection shall be completed not later than the date on which the Secretary, in consultation and concurrence with the agencies identified under subsection (e), establishes with respect to the project study.
Lead agencies
Joint lead agencies
In general
At the discretion of the Secretary and subject to the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and the requirements of section 1506.8 of title 40, Code of Federal Regulations (or successor regulations), including the concurrence of the proposed joint lead agency, a project sponsor may serve as the joint lead agency.
Project sponsor as joint lead agency
A project sponsor that is a State or local governmental entity may—
prepare any environmental review process document under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) required in support of any action or approval by the Secretary if—
the project sponsor complies with all requirements applicable to the Secretary under—
Duties
The Secretary shall ensure that—
Adoption and use of documents
Any environmental document prepared in accordance with this subsection shall be adopted and used by any Federal agency making any determination related to the project study to the same extent that the Federal agency could adopt or use a document prepared by another Federal agency under—
Roles and responsibility of lead agency
With respect to the environmental review process for any project study, the Federal lead agency shall have authority and responsibility—
Participating and cooperating agencies
Identification of jurisdictional agencies
With respect to carrying out the environmental review process for a project study, the Secretary shall identify, as early as practicable in the environmental review process, all Federal, State, and local government agencies and Indian tribes that may—
State authority
If the environmental review process is being implemented by the Secretary for a project study within the boundaries of a State, the State, consistent with State law, may choose to participate in the process and to make subject to the process all State agencies that—
Invitation
In general
The Federal lead agency shall invite, as early as practicable in the environmental review process, any agency identified under paragraph (1) to become a participating or cooperating agency, as applicable, in the environmental review process for the project study.
Deadline
An invitation to participate issued under subparagraph (A) shall set a deadline by which a response to the invitation shall be submitted, which may be extended by the Federal lead agency for good cause.
Procedures
Section 1501.6 of title 40, Code of Federal Regulations (as in effect on June 10, 2014) shall govern the identification and the participation of a cooperating agency.
Federal cooperating agencies
Any Federal agency that is invited by the Federal lead agency to participate in the environmental review process for a project study shall be designated as a cooperating agency by the Federal lead agency unless the invited agency informs the Federal lead agency, in writing, by the deadline specified in the invitation that the invited agency—
Administration
A participating or cooperating agency shall comply with this section and any schedule established under this section.
Effect of designation
Designation as a participating or cooperating agency under this subsection shall not imply that the participating or cooperating agency—
Concurrent reviews
Each participating or cooperating agency shall—
Programmatic compliance
In general
The Secretary shall issue guidance regarding the use of programmatic approaches to carry out the environmental review process that—
complies with—
Requirements
In carrying out paragraph (1), the Secretary shall—
ensure that the programmatic reviews—
use accurate and timely information in the environmental review process, including—
describe—
Coordinated reviews
Coordination plan
Establishment
In general
The Federal lead agency shall, after consultation with and with the concurrence of each participating and cooperating agency and the project sponsor or joint lead agency, as applicable, establish a plan for coordinating public and agency participation in, and comment on, the environmental review process for a project study or a category of project studies.
Incorporation
The plan established under clause (i) shall be incorporated into the project schedule milestones set under section 2282(g)(2) of this title.
Schedule
In general
As soon as practicable but not later than 45 days after the close of the public comment period on a draft environmental impact statement, the Federal lead agency, after consultation with and the concurrence of each participating and cooperating agency and the project sponsor or joint lead agency, as applicable, shall establish, as part of the coordination plan established in subparagraph (A), a schedule for completion of the environmental review process for the project study.
Factors for consideration
In establishing a schedule, the Secretary shall consider factors such as—
Modifications
The Secretary may—
Dissemination
A copy of a schedule established under clause (i) shall be—
Comment deadlines
The Federal lead agency shall establish the following deadlines for comment during the environmental review process for a project study:
Draft environmental impact statements
For comments by Federal and States 1 agencies and the public on a draft environmental impact statement, a period of not more than 60 days after publication in the Federal Register of notice of the date of public availability of the draft environmental impact statement, unless—
Other environmental review processes
For all other comment periods established by the Federal lead agency for agency or public comments in the environmental review process, a period of not more than 30 days after the date on which the materials on which comment is requested are made available, unless—
Deadlines for decisions under other laws
In any case in which a decision under any Federal law relating to a project study, including the issuance or denial of a permit or license, is required to be made by the date described in subsection (h)(5)(B)(ii), the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives—
Involvement of the public
Nothing in this subsection reduces any time period provided for public comment in the environmental review process under applicable Federal law (including regulations).
Transparency reporting
Reporting requirements
Not later than 1 year after June 10, 2014, the Secretary shall establish and maintain an electronic database and, in coordination with other Federal and State agencies, issue reporting requirements to make publicly available the status and progress with respect to compliance with applicable requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et. seq.) and any other Federal, State, or local approval or action required for a project study for which this section is applicable.
Project study transparency
Consistent with the requirements established under subparagraph (A), the Secretary shall publish the status and progress of any Federal, State, or local decision, action, or approval required under applicable laws for each project study for which this section is applicable.
Issue identification and resolution
Cooperation
The Federal lead agency, the cooperating agencies, and any participating agencies shall work cooperatively in accordance with this section to identify and resolve issues that could delay completion of the environmental review process or result in the denial of any approval required for the project study under applicable laws.
Federal lead agency responsibilities
In general
The Federal lead agency shall make information available to the cooperating agencies and participating agencies as early as practicable in the environmental review process regarding the environmental and socioeconomic resources located within the project area and the general locations of the alternatives under consideration.
Data sources
The information under subparagraph (A) may be based on existing data sources, including geographic information systems mapping.
Cooperating and participating agency responsibilities
Based on information received from the Federal lead agency, cooperating and participating agencies shall identify, as early as practicable, any issues of concern regarding the potential environmental or socioeconomic impacts of the project, including any issues that could substantially delay or prevent an agency from granting a permit or other approval that is needed for the project study.
Accelerated issue resolution and elevation
In general
On the request of a participating or cooperating agency or project sponsor, the Secretary shall convene an issue resolution meeting with the relevant participating and cooperating agencies and the project sponsor or joint lead agency, as applicable, to resolve issues that may—
Meeting date
A meeting requested under this paragraph shall be held not later than 21 days after the date on which the Secretary receives the request for the meeting, unless the Secretary determines that there is good cause to extend that deadline.
Notification
On receipt of a request for a meeting under this paragraph, the Secretary shall notify all relevant participating and cooperating agencies of the request, including the issue to be resolved and the date for the meeting.
Elevation of issue resolution
If a resolution cannot be achieved within the 30 day-period beginning on the date of a meeting under this paragraph and a determination is made by the Secretary that all information necessary to resolve the issue has been obtained, the Secretary shall forward the dispute to the heads of the relevant agencies for resolution.
Convention by Secretary
The Secretary may convene an issue resolution meeting under this paragraph at any time, at the discretion of the Secretary, regardless of whether a meeting is requested under subparagraph (A).
Financial penalty provisions
In general
A Federal jurisdictional agency shall complete any required approval or decision for the environmental review process on an expeditious basis using the shortest existing applicable process.
Failure to decide
In general
If a Federal jurisdictional agency fails to render a decision required under any Federal law relating to a project study that requires the preparation of an environmental impact statement or environmental assessment, including the issuance or denial of a permit, license, statement, opinion, or other approval by the date described in clause (ii), the amount of funds made available to support the office of the head of the Federal jurisdictional agency shall be reduced by an amount of funding equal to the amounts specified in subclause (I) or (II) and those funds shall be made available to the division of the Federal jurisdictional agency charged with rendering the decision by not later than 1 day after the applicable date under clause (ii), and once each week thereafter until a final decision is rendered, subject to subparagraph (C)—
Description of date
The date referred to in clause (i) is the later of—
Limitations
In general
No transfer of funds under subparagraph (B) relating to an individual project study shall exceed, in any fiscal year, an amount equal to 1 percent of the funds made available for the applicable agency office.
Failure to decide
The total amount transferred in a fiscal year as a result of a failure by an agency to make a decision by an applicable deadline shall not exceed an amount equal to 5 percent of the funds made available for the applicable agency office for that fiscal year.
Aggregate
Notwithstanding any other provision of law, for each fiscal year, the aggregate amount of financial penalties assessed against each applicable agency office under the Water Resources Reform and Development Act of 2014 and any other Federal law as a result of a failure of the agency to make a decision by an applicable deadline for environmental review, including the total amount transferred under this paragraph, shall not exceed an amount equal to 9.5 percent of the funds made available for the agency office for that fiscal year.
No fault of agency
In general
A transfer of funds under this paragraph shall not be made if the applicable agency described in subparagraph (A) notifies, with a supporting explanation, the Federal lead agency, cooperating agencies, and project sponsor, as applicable, that—
Lack of financial resources
If the agency provides notice under clause (i)(III), the Inspector General of the agency shall—
Limitation
The Federal agency from which funds are transferred pursuant to this paragraph shall not reprogram funds to the office of the head of the agency, or equivalent office, to reimburse that office for the loss of the funds.
Effect of paragraph
Nothing in this paragraph affects or limits the application of, or obligation to comply with, any Federal, State, local, or tribal law.
Memorandum of agreements for early coordination
Sense of Congress
It is the sense of Congress that—
Technical assistance
If requested at any time by a State or project sponsor, the Secretary and other Federal agencies with relevant jurisdiction in the environmental review process, shall, to the maximum extent practicable and appropriate, as determined by the agencies, provide technical assistance to the State or project sponsor in carrying out early coordination activities.
Memorandum of agency agreement
If requested at any time by a State or project sponsor, the Federal lead agency, in consultation with other Federal agencies with relevant jurisdiction in the environmental review process, may establish memoranda of agreement with the project sponsor, Indian tribe, State and local governments, and other appropriate entities to carry out the early coordination activities, including providing technical assistance in identifying potential impacts and mitigation issues in an integrated fashion.
Limitations
Nothing in this section preempts or interferes with—
any obligation to comply with the provisions of any Federal law, including—
Timing of claims
Timing
In general
Notwithstanding any other provision of law, a claim arising under Federal law seeking judicial review of a permit, license, or other approval issued by a Federal agency for a project study shall be barred unless the claim is filed not later than 3 years after publication of a notice in the Federal Register announcing that the permit, license, or other approval is final pursuant to the law under which the agency action is taken, unless a shorter time is specified in the Federal law that allows judicial review.
Applicability
Nothing in this subsection creates a right to judicial review or places any limit on filing a claim that a person has violated the terms of a permit, license, or other approval.
New information
In general
The Secretary shall consider new information received after the close of a comment period if the information satisfies the requirements for a supplemental environmental impact statement under title 40, Code of Federal Regulations (including successor regulations).
Separate action
The preparation of a supplemental environmental impact statement or other environmental document, if required under this section, shall be considered a separate final agency action and the deadline for filing a claim for judicial review of the action shall be 3 years after the date of publication of a notice in the Federal Register announcing the action relating to such supplemental environmental impact statement or other environmental document.
Categorical exclusions
In general
Not later than 180 days after June 10, 2014, the Secretary shall—
publish a review of the survey that includes a description of—
New categorical exclusions
Not later than 1 year after June 10, 2014, if the Secretary has identified a category of activities that merit establishing a categorical exclusion that did not exist on the day before June 10, 2014, based on the review under paragraph (1), the Secretary shall publish a notice of proposed rulemaking to propose that new categorical exclusion, to the extent that the categorical exclusion meets the criteria for a categorical exclusion under section 1508.4 of title 40, Code of Federal Regulations (or successor regulation).
Review of project acceleration reforms
In general
The Comptroller General of the United States shall—
Contents
The reports under paragraph (1) shall include an evaluation of impacts of the reforms carried out under this section on—
Performance measurement
The Secretary shall establish a program to measure and report on progress made toward improving and expediting the planning and environmental review process.
Implementation guidance
The Secretary shall prepare, in consultation with the Council on Environmental Quality and other Federal agencies with jurisdiction over actions or resources that may be impacted by a project, guidance documents that describe the coordinated environmental review processes that the Secretary intends to use to implement this section for the planning of projects, in accordance with the civil works program of the Corps of Engineers and all applicable law.