U.S. Code · Título 42
Energy right-of-way corridors on Federal land
42 U.S.C. § 15926
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Western States
Not later than 2 years after August 8, 2005, the Secretary of Agriculture, the Secretary of Commerce, the Secretary of Defense, the Secretary of Energy, and the Secretary of the Interior (in this section referred to collectively as “the Secretaries”), in consultation with the Federal Energy Regulatory Commission, States, tribal or local units of governments as appropriate, affected utility industries, and other interested persons, shall consult with each other and shall—
Other States
Not later than 4 years after August 8, 2005, the Secretaries, in consultation with the Federal Energy Regulatory Commission, affected utility industries, and other interested persons, shall jointly—
Ongoing responsibilities
The Secretaries, in consultation with the Federal Energy Regulatory Commission, affected utility industries, and other interested parties, shall establish procedures under their respective authorities that—
Considerations
In carrying out this section, the Secretaries shall take into account the need for upgraded and new electricity transmission and distribution facilities to—
Specifications of corridor
A corridor designated under this section shall, at a minimum, specify the centerline, width, and compatible uses of the corridor.
(Pub. L. 109–58, title III, § 368, Aug. 8, 2005, 119 Stat. 727.)