Definitions
In this section:
SING
The term “SING” means the Spallation Neutron Source Instruments Next Generation major item of equipment.
SNS power upgrade
The term “SNS power upgrade” means the Spallation Neutron Source power upgrade described in the 20-year facilities plan of the Office of Science of the Department.
SNS second target station
The term “SNS second target station” means the Spallation Neutron Source second target station described in the 20-year facilities plan of the Office of Science of the Department.
Spallation Neutron Source Facility
The terms “Spallation Neutron Source Facility” and “Facility” mean the completed Spallation Neutron Source scientific user facility located at Oak Ridge National Laboratory, Oak Ridge, Tennessee.
Spallation Neutron Source Project
The terms “Spallation Neutron Source Project” and “Project” means Department Project 99–E–334, Oak Ridge National Laboratory, Oak Ridge, Tennessee.
Spallation Neutron Source Project
In general
The Secretary shall submit to Congress, as part of the annual budget request of the President submitted to Congress, a report on progress on the Spallation Neutron Source Project.
Contents
The report shall include for the Project—
Spallation Neutron Source Facility plan
In general
The Secretary shall develop an operational plan for the Spallation Neutron Source Facility that ensures that the Facility is employed to the full capability of the Facility in support of the study of advanced materials, nanoscience, and other missions of the Office of Science of the Department.
Plan
The operational plan shall—
include a plan for the operation of an effective scientific user program that—
address the status of and, to the maximum extent practicable, costs and schedules for—
Authorization of appropriations
Spallation Neutron Source Project
There is authorized to be appropriated to carry out the Spallation Neutron Source Project for the lifetime of the Project $1,411,700,000 for total project costs, of which—
Spallation Neutron Source Facility
In general
Except as provided in subparagraph (B), there is authorized to be appropriated for the Spallation Neutron Source Facility for—
Insufficient stockpiles of heavy water
If stockpiles of heavy water of the Department are insufficient to meet the needs of the Facility, there is authorized to be appropriated for the Facility $12,000,000 for fiscal year 2007.