U.S. Code · Título 42
Oversight of NSF major multi-user research facility projects
42 U.S.C. § 1862s–2
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Facilities oversight
In general
The Director of the Foundation shall strengthen oversight and accountability over the full life-cycle of each major multi-user research facility project, including planning, development, procurement, construction, operations, and support, and shut-down of the facility, in order to maximize research investment.
Requirements
In carrying out paragraph (1), the Director shall—
continue to maintain a Large Facilities Office to support the research directorates in the development, implementation, and oversight of each major multi-user research facility project, including by—
Facilities full life-cycle costs
In general
Subject to subsection (c)(1), the Director of the Foundation shall require that any pre-award analysis of a major multi-user research facility project includes the development and consideration of the full life-cycle cost (as defined in section 2 of the National Science Foundation Authorization Act of 1998 (42 U.S.C. 1862k note)) in accordance with section 1862n–4 of this title.
Implementation
Based on the pre-award analysis described in paragraph (1), the Director of the Foundation shall include projected operational costs within the Foundation’s out-years as part of the President’s annual budget submission to Congress under section 1105 of title 31.
Cost oversight
Pre-award analysis
In general
The Director of the Foundation and the National Science Board may not approve or execute any agreement to start construction on any proposed major multi-user research facility project unless—
Audits
An external analysis under subparagraph (A)(i) may include an audit.
Exception
The Director of the Foundation, at the Director’s discretion, may waive the requirement under subparagraph (A)(iii) if a similar analysis of the accounting systems was conducted in the prior years.
Construction oversight
The Director of the Foundation shall require for each major multi-user research facility project—
an incurred cost audit of the major multi-user research facility project in accordance with Government Accountability Office Government Auditing Standards—
Operations cost analysis
The Director of the Foundation shall require an independent cost analysis of the operational proposal for each major multi-user research facility project.
Contingency
In general
The Director of the Foundation shall strengthen internal controls to improve oversight of contingency on a major multi-user research facility project.
Requirements
In carrying out paragraph (1), the Director of the Foundation shall—
Use of fees
Sense of Congress
It is the sense of Congress that—
Reporting and recordkeeping
The Director of the Foundation shall establish guidelines for awardees regarding inappropriate expenditures associated with all fee types used in cooperative agreements, including for alcoholic beverages, lobbying, meals or entertainment for non-business purposes, non-business travel, and any other purpose the Director determines is inappropriate.
Oversight implementation progress
The Director of the Foundation shall—
not later than 90 days after January 6, 2017, and periodically thereafter until the completion date, provide a briefing to the appropriate committees of Congress on the response to or progress made toward implementation of—
Definitions
In this section:
Appropriate committees of Congress
The term “appropriate committees of Congress” means the Committee on Commerce, Science, and Transportation and the Committee on Appropriations of the Senate and the Committee on Science, Space, and Technology and the Committee on Appropriations of the House of Representatives.
Major multi-user research facility project
The term “major multi-user research facility project” means a science and engineering facility project that exceeds $100,000,000 in total construction, acquisition, or upgrade costs to the Foundation.
(Pub. L. 114–329, title I, § 110, Jan. 6, 2017, 130 Stat. 2988; Pub. L. 116–283, div. A, title II, § 267, Jan. 1, 2021, 134 Stat. 3502.)