Increased use of recovered mineral component in federally funded projects involving procurement of cement or concrete
42 U.S.C. § 6966a
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Definitions
In this section:
Agency head
The term “agency head” means—
Cement or concrete project
The term “cement or concrete project” means a project for the construction or maintenance of a highway or other transportation facility or a Federal, State, or local government building or other public facility that—
Recovered mineral component
The term “recovered mineral component” means—
Implementation of requirements
In general
Not later than 1 year after August 10, 2005, the Administrator and each agency head shall take such actions as are necessary to implement fully all procurement requirements and incentives in effect as of August 10, 2005 (including guidelines under section 6962 of this title) that provide for the use of cement and concrete incorporating recovered mineral component in cement or concrete projects.
Priority
In carrying out paragraph (1) an agency head shall give priority to achieving greater use of recovered mineral component in cement or concrete projects for which recovered mineral components historically have not been used or have been used only minimally.
Conformance
The Administrator and each agency head shall carry out this subsection in accordance with section 6962 of this title.
Full implementation study
In general
The Administrator, in cooperation with the Secretary of Transportation and the Secretary of Energy, shall conduct a study to determine the extent to which current procurement requirements, when fully implemented in accordance with subsection (b), may realize energy savings and environmental benefits attainable with substitution of recovered mineral component in cement used in cement or concrete projects.
Matters to be addressed
The study shall—
Report
Not later than 30 months after August 10, 2005, the Administrator shall submit to Congress a report on the study.
Additional procurement requirements
Unless the study conducted under subsection (c) identifies any effects or other problems described in subsection (c)(2)(C)(iii) that warrant further review or delay, the Administrator and each agency head shall, not later than 1 year after the release of the report in accordance with subsection (c)(3), take additional actions authorized under this chapter to establish procurement requirements and incentives that provide for the use of cement and concrete with increased substitution of recovered mineral component in the construction and maintenance of cement or concrete projects, so as to—
Effect of section
Nothing in this section affects the requirements of section 6962 of this title (including the guidelines and specifications for implementing those requirements).
(Pub. L. 89–272, title II, § 6005, as added Pub. L. 109–59, title VI, § 6017(a), Aug. 10, 2005, 119 Stat. 1888.)