U.S. Code · Título 42
Phase I sulfur dioxide requirements
42 U.S.C. § 7651c
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Emission limitations
Not later than December 31, 1991, the Administrator shall determine the total tonnage of reductions in the emissions of sulfur dioxide from all utility units in calendar year 1995 that will occur as a result of compliance with the emissions limitation requirements of this section, and shall establish a reserve of allowances equal in amount to the number of tons determined thereby not to exceed a total of 3.50 million tons. In making such a determination, the Administrator shall compute for each unit subject to the emissions limitation requirements of this section the difference between:
Substitutions
The owner or operator of an affected unit under subsection (a) may include in its section 7651g of this title permit application and proposed compliance plan a proposal to reassign, in whole or in part, the affected unit’s sulfur dioxide reduction requirements to any other unit(s) under the control of such owner or operator. Such proposal shall specify—
Administrator’s action on substitution proposals
Eligible phase I extension units
Such extension proposal shall—
In order to determine the number of proposals eligible for allocations from the reserve under subsection (a)(2) and the number of allowances remaining available after each proposal is acted upon, the Administrator shall reduce the total number of allowances remaining available in the reserve by the number of allowances calculated according to subparagraphs (A), (B) and (C) until either no allowances remain available in the reserve for further allocation or all approved proposals have been acted upon. If no allowances remain available in the reserve for further allocation before all proposals have been acted upon by the Administrator, any pending proposals shall be disapproved. The Administrator shall calculate allowances equal to—
Allocation of allowances
Table A.—Affected Sources and Units in Phase I and Their Sulfur Dioxide Allowances (tons)
State
Plant Name
Generator
Phase I Allowances
Alabama
Colbert
1
2
3
4
5
13,570
15,310
15,400
15,410
37,180
E.C. Gaston
1
2
3
4
5
18,100
18,540
18,310
19,280
59,840
Florida
Big Bend
1
2
3
28,410
27,100
26,740
Crist
6
7
19,200
31,680
Georgia
Bowen
1
2
3
4
56,320
54,770
71,750
71,740
Hammond
1
2
3
4
8,780
9,220
8,910
37,640
J. McDonough
1
2
19,910
20,600
Wansley
1
2
70,770
65,430
Yates
1
2
3
4
5
6
7
7,210
7,040
6,950
8,910
9,410
24,760
21,480
Illinois
Baldwin
1
2
3
42,010
44,420
42,550
Coffeen
1
2
11,790
35,670
Grand Tower
4
5,910
Hennepin
2
18,410
Joppa Steam
1
2
3
4
5
6
12,590
10,770
12,270
11,360
11,420
10,620
Kincaid
1
2
31,530
33,810
Meredosia
3
13,890
Vermilion
2
8,880
Indiana
Bailly
7
8
11,180
15,630
Breed
1
18,500
Cayuga
1
2
33,370
34,130
Clifty Creek
1
2
3
4
5
6
20,150
19,810
20,410
20,080
19,360
20,380
E. W. Stout
5
6
7
3,880
4,770
23,610
F. B. Culley
2
3
4,290
16,970
F. E. Ratts
1
2
8,330
8,480
Gibson
1
2
3
4
40,400
41,010
41,080
40,320
H. T. Pritchard
6
5,770
Michigan City
12
23,310
Petersburg
1
2
16,430
32,380
R. Gallagher
1
2
3
4
6,490
7,280
6,530
7,650
Tanners Creek
4
24,820
Wabash River
1
2
3
5
6
4,000
2,860
3,750
3,670
12,280
Warrick
4
26,980
Iowa
Burlington
1
10,710
Des Moines
7
2,320
George Neal
1
1,290
M.L. Kapp
2
13,800
Prairie Creek
4
8,180
Riverside
5
3,990
Kansas
Quindaro
2
4,220
Kentucky
Coleman
1
2
3
11,250
12,840
12,340
Cooper
1
2
7,450
15,320
E.W. Brown
1
2
3
7,110
10,910
26,100
Elmer Smith
1
2
6,520
14,410
Ghent
1
28,410
Green River
4
7,820
H.L. Spurlock
1
22,780
Henderson II
1
2
13,340
12,310
Paradise
3
59,170
Shawnee
10
10,170
Maryland
Chalk Point
1
2
21,910
24,330
C. P. Crane
1
2
10,330
9,230
Morgantown
1
2
35,260
38,480
Michigan
J. H. Campbell
1
2
19,280
23,060
Minnesota
High Bridge
6
4,270
Mississippi
Jack Watson
4
5
17,910
36,700
Missouri
Asbury
1
16,190
James River
5
4,850
Labadie
1
2
3
4
40,110
37,710
40,310
35,940
Montrose
1
2
3
7,390
8,200
10,090
New Madrid
1
2
28,240
32,480
Sibley
3
15,580
Sioux
1
2
22,570
23,690
Thomas Hill
1
2
10,250
19,390
New Hampshire
Merrimack
1
2
10,190
22,000
New Jersey
B.L. England
1
2
9,060
11,720
New York
Dunkirk
3
4
12,600
14,060
Greenidge
4
7,540
Milliken
1
2
11,170
12,410
Northport
1
2
3
19,810
24,110
26,480
Port Jefferson
3
4
10,470
12,330
Ohio
Ashtabula
5
16,740
Avon Lake
8
9
11,650
30,480
Cardinal
1
2
34,270
38,320
Conesville
1
2
3
4
4,210
4,890
5,500
48,770
Eastlake
1
2
3
4
5
7,800
8,640
10,020
14,510
34,070
Edgewater
4
5,050
Gen. J.M. Gavin
1
2
79,080
80,560
Kyger Creek
1
2
3
4
5
19,280
18,560
17,910
18,710
18,740
Miami Fort
5
6
7
760
11,380
38,510
Muskingum River
1
2
3
4
5
14,880
14,170
13,950
11,780
40,470
Niles
1
2
6,940
9,100
Picway
5
4,930
R.E. Burger
3
4
5
6,150
10,780
12,430
W.H. Sammis
5
6
7
24,170
39,930
43,220
W.C. Beckjord
5
6
8,950
23,020
Pennsylvania
Armstrong
1
2
14,410
15,430
Brunner Island
1
2
3
27,760
31,100
53,820
Cheswick
1
39,170
Conemaugh
1
2
59,790
66,450
Hatfield’s Ferry
1
2
3
37,830
37,320
40,270
Martins Creek
1
2
12,660
12,820
Portland
1
2
5,940
10,230
Shawville
1
2
3
4
10,320
10,320
14,220
14,070
Sunbury
3
4
8,760
11,450
Tennessee
Allen
1
2
3
15,320
16,770
15,670
Cumberland
1
2
86,700
94,840
Gallatin
1
2
3
4
17,870
17,310
20,020
21,260
Johnsonville
1
2
3
4
5
6
7
8
9
10
7,790
8,040
8,410
7,990
8,240
7,890
8,980
8,700
7,080
7,550
West Virginia
Albright
3
12,000
Fort Martin
1
2
41,590
41,200
Harrison
1
2
3
48,620
46,150
41,500
Kammer
1
2
3
18,740
19,460
17,390
Mitchell
1
2
43,980
45,510
Mount Storm
1
2
3
43,720
35,580
42,430
Wisconsin
Edgewater
4
24,750
La Crosse/Genoa
3
22,700
Nelson Dewey
1
2
6,010
6,680
N. Oak Creek
1
2
3
4
5,220
5,140
5,370
6,320
Pulliam
8
7,510
S. Oak Creek
5
6
7
8
9,670
12,040
16,180
15,790
Energy conservation and renewable energy
Definitions
As used in this subsection:
Qualified energy conservation measure
The term “qualified energy conservation measure” means a cost effective measure, as identified by the Administrator in consultation with the Secretary of Energy, that increases the efficiency of the use of electricity provided by an electric utility to its customers.
Qualified renewable energy
The term “qualified renewable energy” means energy derived from biomass, solar, geothermal, or wind as identified by the Administrator in consultation with the Secretary of Energy.
Electric utility
The term “electric utility” means any person, State agency, or Federal agency, which sells electric energy.
Allowances for emissions avoided through energy conservation and renewable energy
In general
The regulations under paragraph (4) of this subsection shall provide that for each ton of sulfur dioxide emissions avoided by an electric utility, during the applicable period, through the use of qualified energy conservation measures or qualified renewable energy, the Administrator shall allocate a single allowance to such electric utility, on a first-come-first-served basis from the Conservation and Renewable Energy Reserve established under subsection (g), up to a total of 300,000 allowances for allocation from such Reserve.
Requirements for issuance
The Administrator shall allocate allowances to an electric utility under this subsection only if all of the following requirements are met:
Period of applicability
Allowances under this subsection shall be allocated only with respect to kilowatt hours of electric energy saved by qualified energy conservation measures or generated by qualified renewable energy after January 1, 1992 and before the earlier of (i) December 31, 2000, or (ii) the date on which any electric utility steam generating unit owned or operated by the electric utility to which the allowances are allocated becomes subject to this subchapter (including those sources that elect to become affected by this subchapter, pursuant to section 7651i of this title).
Determination of avoided emissions
8 Application
In order to receive allowances under this subsection, an electric utility shall make an application which—
Avoided emissions from qualified energy conservation measures
For the purposes of this subsection, the emission tonnage deemed avoided by reason of the implementation of qualified energy conservation measures for any calendar year shall be a tonnage equal to the product of multiplying—
Avoided emissions from the use of qualified renewable energy
The emissions tonnage deemed avoided by reason of the use of qualified renewable energy by an electric utility for any calendar year shall be a tonnage equal to the product of multiplying—
Prohibitions
Savings provision
Nothing in this subsection precludes a State or State regulatory authority from providing additional incentives to utilities to encourage investment in demand-side resources.
Regulations
Not later than 18 months after November 15, 1990, and in conjunction with the regulations required to be promulgated under subsections (b) and (c), the Administrator shall, in consultation with the Secretary of Energy, promulgate regulations under this subsection. Such regulations shall list energy conservation measures and renewable energy sources which may be treated as qualified energy conservation measures and qualified renewable energy for purposes of this subsection. Allowances shall only be allocated if all requirements of this subsection and the rules promulgated to implement this subsection are complied with. The Administrator shall review the determinations of each State regulatory authority under this subsection to encourage consistency from electric utility to electric utility and from State to State in accordance with the Administrator’s rules. The Administrator shall publish the findings of this review no less than annually.
Conservation and Renewable Energy Reserve
The Administrator shall establish a Conservation and Renewable Energy Reserve under this subsection. Beginning on January 1, 1995, the Administrator may allocate from the Conservation and Renewable Energy Reserve an amount equal to a total of 300,000 allowances for emissions of sulfur dioxide pursuant to section 7651b of this title. In order to provide 300,000 allowances for such reserve, in each year beginning in calendar year 2000 and until calendar year 2009, inclusive, the Administrator shall reduce each unit’s basic Phase II allowance allocation on the basis of its pro rata share of 30,000 allowances. If allowances remain in the reserve after January 2, 2010, the Administrator shall allocate such allowances for affected units under section 7651d of this title on a pro rata basis. For purposes of this subsection, for any unit subject to the emissions limitation requirements of section 7651d of this title, the term “pro rata basis” refers to the ratio which the reductions made in such unit’s allowances in order to establish the reserve under this subsection bears to the total of such reductions for all such units.
Alternative allowance allocation for units in certain utility systems with optional baseline
Optional baseline for units in certain systems
In the case of a unit subject to the emissions limitation requirements of this section which (as of November 15, 1990)—
Allowance allocation
Whenever a unit referred to in paragraph (1) elects to calculate its baseline as provided in clause (ii) of paragraph (1), the Administrator shall allocate allowances for the unit pursuant to section 7651b(a)(1) of this title, this section, and section 7651d of this title (as basic Phase II allowance allocations) in an amount equal to the baseline selected multiplied by the lower of the average annual emission rate for such unit in 1989, or 1.0 lbs./mmBtu. Such allowance allocation shall be in lieu of any allocation of allowances under this section and section 7651d of this title.
(July 14, 1955, ch. 360, title IV, § 404, as added Pub. L. 101–549, title IV, § 401, Nov. 15, 1990, 104 Stat. 2592.)