U.S. Code · Título 47
Identification of reallocable frequencies
47 U.S.C. § 923
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Identification required
The Secretary shall, within 18 months after August 10, 1993, and within 6 months after August 5, 1997, prepare and submit to the President and the Congress a report identifying and recommending for reallocation bands of frequencies—
Minimum amount of spectrum recommended
Initial reallocation report
In accordance with the provisions of this section, the Secretary shall recommend for reallocation in the initial report required by subsection (a), for use other than by Federal Government stations under section 305 of the 1934 Act (47 U.S.C. 305), bands of frequencies that in the aggregate span not less than 200 megahertz, that are located below 5 gigahertz, and that meet the criteria specified in paragraphs (1) through (5) of subsection (a). Such bands of frequencies shall include bands of frequencies, located below 3 gigahertz, that span in the aggregate not less than 100 megahertz.
Mixed uses permitted to be counted
Bands of frequencies which a report of the Secretary under subsection (a) or (d)(1) recommends be partially retained for use by Federal Government stations, but which are also recommended to be reallocated to be made available under the 1934 Act [47 U.S.C. 151 et seq.] for use by non-Federal stations, may be counted toward the minimum spectrum required by paragraph (1) or (3) of this subsection, except that—
Second reallocation report
In accordance with the provisions of this section, the Secretary shall recommend for reallocation in the second report required by subsection (a), for use other than by Federal Government stations under section 305 of the 1934 Act (47 U.S.C. 305), a band or bands of frequencies that—
Criteria for identification
Needs of the Federal Government
In determining whether a band of frequencies meets the criteria specified in subsection (a)(2), the Secretary shall—
seek to promote—
seek to avoid—
Feasibility of use
In determining whether a frequency band meets the criteria specified in subsection (a)(3), the Secretary shall—
Analysis of benefits
In determining whether a band of frequencies meets the criteria specified in subsection (a)(5), the Secretary shall consider—
Power agency frequencies
Applicability of criteria
The criteria specified by subsection (a) shall be deemed not to be met for any purpose under this subchapter with regard to any frequency assignment to, or any frequency assignment used by, a Federal power agency for the purpose of withdrawing that assignment.
Mixed use eligibility
The frequencies assigned to any Federal power agency may only be eligible for mixed use under subsection (b)(2) in geographically separate areas, but in those cases where a frequency is to be shared by an affected Federal power agency and a non-Federal user, such use by the non-Federal user shall not cause harmful interference to the affected Federal power agency or adversely affect the reliability of its power system.
“Federal power agency” defined
As used in this paragraph, the term “Federal power agency” means the Tennessee Valley Authority, the Bonneville Power Administration, the Western Area Power Administration, the Southwestern Power Administration, the Southeastern Power Administration, or the Alaska Power Administration.
Limitation on reallocation
None of the frequencies recommended for reallocation in the reports required by this subsection shall have been recommended, prior to August 10, 1993, for reallocation to non-Federal use by international agreement.
Procedure for identification of reallocable bands of frequencies
Submission of preliminary identification to Congress
Within 6 months after August 10, 1993, the Secretary shall prepare, make publicly available, and submit to the President, the Congress, and the Commission a report which makes a preliminary identification of reallocable bands of frequencies which meet the criteria established by this section.
Public comment
The Secretary shall provide interested persons with the opportunity to submit, within 90 days after the date of its publication, written comment on the preliminary report required by paragraph (1). The Secretary shall immediately transmit a copy of any such comment to the Commission.
Comment and recommendations from Commission
The Commission shall, within 90 days after the conclusion of the period for comment provided pursuant to paragraph (2), submit to the Secretary the Commission’s analysis of such comments and the Commission’s recommendations for responses to such comments, together with such other comments and recommendations as the Commission deems appropriate.
Direct discussions
The Secretary shall encourage and provide opportunity for direct discussions among commercial representatives and Federal Government users of the spectrum to aid the Secretary in determining which frequencies to recommend for reallocation. The Secretary shall provide notice to the public and the Commission of any such discussions, including the name or names of any businesses or other persons represented in such discussions. A representative of the Commission (and of the Secretary at the election of the Secretary) shall be permitted to attend any such discussions. The Secretary shall provide the public and the Commission with an opportunity to comment on the results of any such discussions prior to the submission of the initial report required by subsection (a).
Timetable for reallocation and limitation
Timetable required
The Secretary shall, as part of the reports required by subsections (a) and (d)(1), include a timetable that recommends effective dates by which the President shall withdraw or limit assignments of the frequencies specified in such reports.
Expedited reallocation
Required reallocation
The Secretary shall, as part of the report required by subsection (d)(1), specifically identify and recommend for immediate reallocation bands of frequencies that in the aggregate span not less than 50 megahertz, that meet the criteria described in subsection (a), and that can be made available for reallocation immediately upon issuance of the report required by subsection (d)(1). Such bands of frequencies shall include bands of frequencies, located below 3 gigahertz, that in the aggregate span not less than 25 megahertz.
Permitted reallocation
The Secretary may, as part of such report, identify and recommend bands of frequencies for immediate reallocation for a mixed use pursuant to subsection (b)(2), but such bands of frequencies may not count toward the minimums required by subparagraph (A).
Delayed effective dates
In setting the recommended delayed effective dates, the Secretary shall—
Additional reallocation report
If the Secretary receives a notice from the Commission pursuant to section 3002(c)(5) of the Balanced Budget Act of 1997, the Secretary shall prepare and submit to the President, the Commission, and the Congress a report recommending for reallocation for use other than by Federal Government stations under section 305 of the 1934 Act (47 U.S.C. 305), bands of frequencies that are suitable for the licensees identified in the Commission’s notice. The Commission shall, not later than one year after receipt of such report, prepare, submit to the President and the Congress, and implement, a plan for the immediate allocation and assignment of such frequencies under the 1934 Act [47 U.S.C. 151 et seq.] to incumbent licensees described in the Commission’s notice.
Relocation of and spectrum sharing by Federal Government stations
Eligible Federal entities
Any Federal entity that operates a Federal Government station that incurs relocation or sharing costs because of planning for an auction of eligible spectrum frequencies or the reallocation of eligible spectrum frequencies from Federal use to exclusive non-Federal use or to shared use shall receive payment for such relocation or sharing costs from the Spectrum Relocation Fund, in accordance with this section and section 928 of this title. For purposes of this paragraph, Federal power agencies exempted under subsection (c)(4) that choose to relocate from the frequencies identified for reallocation pursuant to subsection (a) are eligible to receive payment under this paragraph.
Eligible frequencies
The bands of eligible frequencies for purposes of this section are as follows:
Relocation or sharing costs defined
In general
For purposes of this section and section 928 of this title, the term “relocation or sharing costs” means the costs incurred by a Federal entity in connection with the auction of spectrum frequencies or the sharing of spectrum frequencies (including the auction or a planned auction of the rights to use spectrum frequencies on a shared basis with such entity) in order to achieve comparable capability of systems as before the relocation or sharing arrangement. Such term includes, with respect to relocation or sharing, as the case may be—
the costs of research, engineering studies, economic analyses, or other expenses reasonably incurred in connection with—
the one-time costs of any modification of equipment reasonably necessary—
Comparable capability of systems
For purposes of subparagraph (A), comparable capability of systems—
Notice to Commission of estimated relocation or sharing costs
Notice to congressional committees and GAO
The NTIA shall, at the time of providing an initial estimate of relocation or sharing costs to the Commission under paragraph (4)(A), submit to 1 Committees on Appropriations and Energy and Commerce of the House of Representatives for approval, to the Committees on Appropriations and Commerce, Science, and Transportation of the Senate for approval, and to the Comptroller General a copy of such estimate and the timelines for relocation or sharing. Unless disapproved within 30 days, the estimate shall be approved. If disapproved, the NTIA may resubmit a revised initial estimate.
Implementation of procedures
The NTIA shall take such actions as necessary to ensure the timely relocation of Federal entities’ spectrum-related operations from frequencies described in paragraph (2) to frequencies or facilities of comparable capability and to ensure the timely implementation of arrangements for the sharing of frequencies described in such paragraph. Upon a finding by the NTIA that a Federal entity has achieved comparable capability of systems, the NTIA shall terminate or limit the entity’s authorization and notify the Commission that the entity’s relocation has been completed or sharing arrangement has been implemented. The NTIA shall also terminate such entity’s authorization if the NTIA determines that the entity has unreasonably failed to comply with the timeline for relocation or sharing submitted by the Director of the Office of Management and Budget under section 928(d)(2)(C) of this title.
Development and publication of relocation or sharing transition plans
Development of transition plan by Federal entity
Not later than 240 days before the commencement of any auction of eligible frequencies described in subsection (g)(2), a Federal entity shall submit to the NTIA and to the Technical Panel established by paragraph (3) a transition plan for the implementation by such entity of the relocation or sharing arrangement. The NTIA shall specify, after public input, a common format for all Federal entities to follow in preparing transition plans under this paragraph.
Contents of transition plan
The transition plan required by paragraph (1) shall include the following information:
The plans and timelines of the Federal entity for—
Technical Panel
Establishment
There is established within the NTIA a panel to be known as the Technical Panel.
Membership
Number and appointment
The Technical Panel shall be composed of 3 members, to be appointed as follows:
Qualifications
Each member of the Technical Panel shall be a radio engineer or a technical expert.
Initial appointment
The initial members of the Technical Panel shall be appointed not later than 180 days after February 22, 2012.
Terms
The term of a member of the Technical Panel shall be 18 months, and no individual may serve more than 1 consecutive term.
Vacancies
Any member appointed to fill a vacancy occurring before the expiration of the term for which the member’s predecessor was appointed shall be appointed only for the remainder of that term. A member may serve after the expiration of that member’s term until a successor has taken office. A vacancy shall be filled in the manner in which the original appointment was made.
No compensation
The members of the Technical Panel shall not receive any compensation for service on the Technical Panel. If any such member is an employee of the agency of the official that appointed such member to the Technical Panel, compensation in the member’s capacity as such an employee shall not be considered compensation under this clause.
Administrative support
The NTIA shall provide the Technical Panel with the administrative support services necessary to carry out its duties under this subsection, subsection (i), and section 928(g)(2)(E) of this title.
Regulations
Not later than 180 days after February 22, 2012, the NTIA shall, after public notice and comment and subject to approval by the Director of OMB, adopt regulations to govern the workings of the Technical Panel.
Certain requirements inapplicable
Chapter 10 of title 5 and sections 552 and 552b of title 5 shall not apply to the Technical Panel.
Review of plan by Technical Panel
In general
Not later than 30 days after the submission of the plan under paragraph (1), the Technical Panel shall submit to the NTIA and to the Federal entity a report on the sufficiency of the plan, including whether the plan includes the information required by paragraph (2) and an assessment of the reasonableness of the proposed timelines and estimated relocation or sharing costs, including the costs of any proposed expansion of the capabilities of a Federal system in connection with relocation or sharing.
Insufficiency of plan
If the Technical Panel finds the plan insufficient, the Federal entity shall, not later than 90 days after the submission of the report by the Technical Panel under subparagraph (A), submit to the Technical Panel a revised plan. Such revised plan shall be treated as a plan submitted under paragraph (1).
Publication of transition plan
Not later than 120 days before the commencement of the auction described in paragraph (1), the NTIA shall make the transition plan publicly available on its website.
Updates of transition plan
As the Federal entity implements the transition plan, it shall periodically update the plan to reflect any changed circumstances, including changes in estimated relocation or sharing costs or the timeline for relocation or sharing. The NTIA shall make the updates available on its website.
Classified and other sensitive information
Classified information
If any of the information required to be included in the transition plan of a Federal entity is classified information (as defined in section 798(b) of title 18), the entity shall—
include in the plan—
Regulations
Not later than 180 days after February 22, 2012, the NTIA, in consultation with the Director of OMB and the Secretary of Defense, shall adopt regulations to ensure that the information publicly released under paragraph (5) or (6) does not contain classified information or other sensitive information.
Dispute resolution process
In general
If a dispute arises between a Federal entity and a non-Federal user regarding the execution, timing, or cost of the transition plan submitted by the Federal entity under subsection (h)(1), the Federal entity or the non-Federal user may request that the NTIA establish a dispute resolution board to resolve the dispute.
Establishment of board
In general
If the NTIA receives a request under paragraph (1), it shall establish a dispute resolution board.
Membership and appointment
The dispute resolution board shall be composed of 3 members, as follows:
Chair
The representative of OMB shall be the Chair of the dispute resolution board.
Vacancies
Any vacancy in the dispute resolution board shall be filled in the manner in which the original appointment was made.
No compensation
The members of the dispute resolution board shall not receive any compensation for service on the board. If any such member is an employee of the agency of the official that appointed such member to the board, compensation in the member’s capacity as such an employee shall not be considered compensation under this subparagraph.
Termination of board
The dispute resolution board shall be terminated after it rules on the dispute that it was established to resolve and the time for appeal of its decision under paragraph (7) has expired, unless an appeal has been taken under such paragraph. If such an appeal has been taken, the board shall continue to exist until the appeal process has been exhausted and the board has completed any action required by a court hearing the appeal.
Procedures
The dispute resolution board shall meet simultaneously with representatives of the Federal entity and the non-Federal user to discuss the dispute. The dispute resolution board may require the parties to make written submissions to it.
Deadline for decision
The dispute resolution board shall rule on the dispute not later than 30 days after the request was made to the NTIA under paragraph (1).
Assistance from Technical Panel
The Technical Panel established under subsection (h)(3) shall provide the dispute resolution board with such technical assistance as the board requests.
Administrative support
The NTIA shall provide the dispute resolution board with the administrative support services necessary to carry out its duties under this subsection.
Appeals
A decision of the dispute resolution board may be appealed to the United States Court of Appeals for the District of Columbia Circuit by filing a notice of appeal with that court not later than 30 days after the date of such decision. Each party shall bear its own costs and expenses, including attorneys’ fees, for any appeal under this paragraph.
Regulations
Not later than 180 days after February 22, 2012, the NTIA shall, after public notice and comment and subject to approval by OMB, adopt regulations to govern the working of any dispute resolution boards established under paragraph (2)(A) and the role of the Technical Panel in assisting any such board.
Certain requirements inapplicable
Chapter 10 of title 5 and sections 552 and 552b of title 5 shall not apply to a dispute resolution board established under paragraph (2)(A).
Relocation prioritized over sharing
In general
In evaluating a band of frequencies for possible reallocation for exclusive non-Federal use or shared use, the NTIA shall give priority to options involving reallocation of the band for exclusive non-Federal use and shall choose options involving shared use only when it determines, in consultation with the Director of the Office of Management and Budget, that relocation of a Federal entity from the band is not feasible because of technical or cost constraints.
Notification of Congress when sharing chosen
If the NTIA determines under paragraph (1) that relocation of a Federal entity from the band is not feasible, the NTIA shall notify the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Energy and Commerce of the House of Representatives of the determination, including the specific technical or cost constraints on which the determination is based.
Federal action to expedite spectrum transfer
Any Federal Government station which operates on electromagnetic spectrum that has been identified in any reallocation report under this section shall, to the maximum extent practicable through the use of the authority granted under subsection (g) and any other applicable provision of law, take action to relocate its spectrum use to other frequencies that are reserved for Federal use or to consolidate its spectrum use with other Federal Government stations in a manner that maximizes the spectrum available for non-Federal use.
“Federal entity” defined
For purposes of this section, the term “Federal entity” means any department, agency, or other instrumentality of the Federal Government that utilizes a Government station license obtained under section 305 of the 1934 Act (47 U.S.C. 305).
(Pub. L. 102–538, title I, § 113, as added Pub. L. 103–66, title VI, § 6001(a)(3), Aug. 10, 1993, 107 Stat. 380; amended Pub. L. 105–33, title III, § 3002(d)(1), (e)(1)–(3), Aug. 5, 1997, 111 Stat. 262, 264, 265; Pub. L. 105–261, div. A, title X, § 1064(c), Oct. 17, 1998, 112 Stat. 2132; Pub. L. 106–65, div. A, title X, § 1062(c)(2), Oct. 5, 1999, 113 Stat. 768; Pub. L. 108–494, title II, § 202, Dec. 23, 2004, 118 Stat. 3991; Pub. L. 112–96, title VI, § 6701(a), Feb. 22, 2012, 126 Stat. 245; Pub. L. 114–74, title X, § 1005(b), (c), Nov. 2, 2015, 129 Stat. 623, 624; Pub. L. 117–286, § 4(a)(299), Dec. 27, 2022, 136 Stat. 4338.)