Identification of projects
Project submission
Any Project Sponsor may submit, so long as the Oversight Board is in operation, any existing, ongoing, or proposed project to the Revitalization Coordinator. The Revitalization Coordinator shall require such submission to include—
in addition to the requirements found in subparagraphs (A) through (E), the Revitalization Coordinator may require such submission to include any or all of the following criteria that assess how the project will—
Identification of relevant Puerto Rico Agencies
Within 20 days of receiving a project submission under paragraph (1), the Revitalization Coordinator shall, in consultation with the Governor, identify all Puerto Rico Agencies that will have a role in the permitting, approval, authorizing, or other activity related to the development of such project submission.
Expedited Permitting Process
Submission of Expedited Permitting Process
Not later than 20 days after receiving a project submission, each Puerto Rico Agency identified in paragraph (1) shall submit to the Revitalization Coordinator the Agency’s Expedited Permitting Process.
Failure to provide Expedited Permitting Process
If a Puerto Rico Agency fails to provide an Expedited Permitting Process within 20 days of receiving a project submission, the Revitalization Coordinator shall consult with the Governor to develop within 20 days an Expedited Permitting Process for the Agency.
Implementation and prioritization
The Revitalization Coordinator shall require Puerto Rico Agencies to implement the Expedited Permitting Process for Critical Projects. Critical Projects shall be prioritized to the maximum extent possible in each Puerto Rico Agency regardless of any agreements transferring or delegating permitting authority to any other Territorial Instrumentality or municipality.
Critical Project Report
In general
For each submitted project, the Revitalization Coordinator in consultation with the Governor and relevant Puerto Rico Agencies identified in subsection (a)(2) shall develop a Critical Project Report within 60 days of the project submission, which shall include:
Public involvement
Immediately following the completion of the Critical Project Report, the Revitalization Coordinator shall make such Critical Project Report public and allow a period of 30 days for the submission of comments by residents of Puerto Rico specifically on matters relating to the designation of a project as a Critical Project. The Revitalization Coordinator shall respond to the comments within 30 days of closing the coming 2 period and make the responses publicly available.
Submission to Oversight Board
Not later than 5 days after the Revitalization Coordinator has responded to the comments under paragraph (2), the Revitalization Coordinator shall submit the Critical Project Report to the Oversight Board.
Action by the Oversight Board
Not later than 30 days after receiving the Critical Project Report, the Oversight Board, by majority vote, shall approve or disapprove the project as a Critical Project, if the Oversight Board—
(Pub. L. 114–187, title V, § 503, June 30, 2016, 130 Stat. 598.)