U.S. Code · Título 49
Grant conditions
49 U.S.C. § 22905
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
Buy America.—
The Secretary of Transportation may waive paragraph (1) of this subsection if the Secretary finds that—
If the Secretary determines that it is necessary to waive the application of paragraph (1) based on a finding under paragraph (2), the Secretary shall, before the date on which such finding takes effect—
The Secretary of Transportation may not make a waiver under paragraph (2) of this subsection for goods produced in a foreign country if the Secretary, in consultation with the United States Trade Representative, decides that the government of that foreign country—
A person is ineligible to receive a contract or subcontract made with amounts authorized under this chapter if a court or department, agency, or instrumentality of the Government decides the person intentionally—
Operators Deemed Rail Carriers and Employers for Certain Purposes.—
A person that conducts rail operations over rail infrastructure constructed or improved with funding provided in whole or in part in a grant made under this chapter shall be considered a rail carrier as defined in section 10102(5) of this title for purposes of this title and any other statute that adopts that definition or in which that definition applies, including—
Grant Conditions.—
The Secretary shall require as a condition of making any grant under this chapter for a project that uses rights-of-way owned by a railroad that—
a written agreement exist between the applicant and the railroad regarding such use and ownership, including—
the applicant agrees to comply with—
Replacement of Existing Intercity Passenger Rail Service.—
Collective bargaining agreement for intercity passenger rail projects.—
Any entity providing intercity passenger railroad transportation that begins operations after the date of enactment of this Act 1 on a project funded in whole or in part by grants made under this chapter and replaces intercity rail passenger service that was provided by Amtrak, unless such service was provided solely by Amtrak to another entity or unless Amtrak ceased providing intercity passenger railroad transportation over the affected route more than 3 years before the commencement of new service, as of such date shall enter into an agreement with the authorized bargaining agent or agents for adversely affected employees of the predecessor provider that—
Immediate replacement service.—
Negotiations.—
If the replacement of preexisting intercity rail passenger service occurs concurrent with or within a reasonable time before the commencement of the replacing entity’s rail passenger service, the replacing entity shall give written notice of its plan to replace existing rail passenger service to the authorized collective bargaining agent or agents for the potentially adversely affected employees of the predecessor provider at least 90 days before the date on which it plans to commence service. Within 5 days after the date of receipt of such written notice, negotiations between the replacing entity and the collective bargaining agent or agents for the employees of the predecessor provider shall commence for the purpose of reaching agreement with respect to all matters set forth in subparagraphs (A) through (D) of paragraph (1). The negotiations shall continue for 30 days or until an agreement is reached, whichever is sooner. If at the end of 30 days the parties have not entered into an agreement with respect to all such matters, the unresolved issues shall be submitted for arbitration in accordance with the procedure set forth in subparagraph (B).Arbitration.—
If an agreement has not been entered into with respect to all matters set forth in subparagraphs (A) through (D) of paragraph (1) as described in subparagraph (A) of this paragraph, the parties shall select an arbitrator. If the parties are unable to agree upon the selection of such arbitrator within 5 days, either or both parties shall notify the National Mediation Board, which shall provide a list of seven arbitrators with experience in arbitrating rail labor protection disputes. Within 5 days after such notification, the parties shall alternately strike names from the list until only 1 name remains, and that person shall serve as the neutral arbitrator. Within 45 days after selection of the arbitrator, the arbitrator shall conduct a hearing on the dispute and shall render a decision with respect to the unresolved issues among the matters set forth in subparagraphs (A) through (D) of paragraph (1). The arbitrator shall be guided by prevailing national standard rates of pay, benefits, and working conditions for comparable work. This decision shall be final, binding, and conclusive upon the parties. The salary and expenses of the arbitrator shall be borne equally by the parties; all other expenses shall be paid by the party incurring them.Service commencement.—
A replacing entity under this subsection shall commence service only after an agreement is entered into with respect to the matters set forth in subparagraphs (A) through (D) of paragraph (1) or the decision of the arbitrator has been rendered.Subsequent replacement of service.—
If the replacement of existing rail passenger service takes place within 3 years after the replacing entity commences intercity passenger rail service, the replacing entity and the collective bargaining agent or agents for the adversely affected employees of the predecessor provider shall enter into an agreement with respect to the matters set forth in subparagraphs (A) through (D) of paragraph (1). If the parties have not entered into an agreement with respect to all such matters within 60 days after the date on which the replacing entity replaces the predecessor provider, the parties shall select an arbitrator using the procedures set forth in paragraph (2)(B), who shall, within 20 days after the commencement of the arbitration, conduct a hearing and decide all unresolved issues. This decision shall be final, binding, and conclusive upon the parties.Inapplicability to Certain Rail Operations.—
Nothing in this section applies to—
Limitation.—
No grants shall be provided under this chapter for commuter rail passenger transportation (as defined in section 24102(3)).(Added Pub. L. 110–432, div. B, title III, § 301(a), Oct. 16, 2008, 122 Stat. 4942, § 24405; amended Pub. L. 114–94, div. A, title XI, § 11303(b)(1)(D), Dec. 4, 2015, 129 Stat. 1654; renumbered § 22905 and amended Pub. L. 115–420, § 7(a)(1), (b)(1)(B), (2)(C), Jan. 3, 2019, 132 Stat. 5445, 5446; Pub. L. 117–58, div. B, title I, § 21301(j)(4)(D), Nov. 15, 2021, 135 Stat. 693.)