U.S. Code · Título 49
Alternative project delivery
49 U.S.C. § 47142
Office of the Law Revision Counsel · release 119-142
Se muestra el texto operativo de la sección. Las notas estatutarias y el historial de enmiendas están en la fuente oficial.
In General.—
The Secretary of Transportation may approve an application of an airport sponsor under this section to authorize the airport sponsor to award a covered project delivery contract using a selection process permitted under applicable State or local law if—
Reimbursement of Costs.—
The Administrator may reimburse an airport sponsor for design and construction costs incurred before a grant is made pursuant to this section if the project is approved by the Administrator in advance and is carried out in accordance with all administrative and statutory requirements that would have been applicable under this chapter if the project were carried out after a grant agreement had been executed.Pilot Program.—
Pilot program.—
Not later than 270 days after the date of enactment of this section, the Secretary shall establish a pilot program under which the Administrator may award grants for integrated project delivery contracts, as described in subsection (d)(2), to carry out up to 5 building construction projects at airports in the United States with a grant awarded under section 47104.Application.—
Eligibility.—
A sponsor of an airport may submit to the Secretary an application, in such time and manner and containing such information as the Secretary may require, to carry out a building construction project under the pilot program that would otherwise be eligible for assistance under this chapter.Approval.—
The Secretary may approve the application of a sponsor of an airport submitted under paragraph (1) to authorize such sponsor to award an integrated project delivery contract using a selection process permitted under applicable State or local law if—
Reimbursement of costs.—
In general.—
The Secretary may reimburse a sponsor of an airport for any design or construction costs incurred before a grant is made pursuant to this section if—
Accounting.—
Reimbursement of costs shall be based on transparent cost accounting or open book cost accounting.Covered Project Delivery Contract Defined.—
In this section, the term “covered project delivery contract” means—
a single contract for the delivery of a whole project that—
(Added Pub. L. 108–176, title I, § 181(a), Dec. 12, 2003, 117 Stat. 2515; amended Pub. L. 118–63, title VII, § 723(a), May 16, 2024, 138 Stat. 1265.)